Select Board reviews storage plan for Waukewan Dam penstock pipes ahead of fall repairs
Summary
Town Manager Judie Milner and Public Works Director Craig Hale described a storage agreement to hold penstock piping at the old landfill landing while the Waukewan Dam owner orders 20-week‑lead-time pipes for a FEMA-backed repair; attorneys for the town and project have agreed to the draft contract.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Town Manager Judie Milner told the Select Board the Waukewan Dam owner received a letter of deficiency and must replace penstock piping, but the specialized pipe has roughly a 20‑week lead time. Milner said contractors cannot start on-site work until the pipe deliveries begin, so the owner asked to store the pipe on town property in the old landfill’s second landing.
Public Works Director Craig Hale said the second landing was constructed for material storage and is accessible through the highway garage gates so deliveries would not interfere with the transfer station. He said roughly three sections of pipe fit per tractor‑trailer, so deliveries will arrive on multiple trucks, and that access to the dock would be coordinated through his office.
Milner said the project attorney and the town attorney negotiated the storage agreement, which the board reviewed, and Chair Aiken noted the project is FEMA‑funded and requires American‑made materials, reinforcing the concern about long lead times. The Select Board directed staff to continue coordinating logistics and to place any final storage agreement on an upcoming agenda for formal approval if needed.