Peter reports framing, asbestos removal and cellar work as new library moves toward finishing phase
Summary
Project lead Peter told the board that framing is nearly complete, old windows containing asbestos putty have been removed, and subcontractors are starting mechanical, electrical and plumbing rough‑ins; Naylor & Breen expect to pause mid‑February and return in mid‑March for interior finishing.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Peter, the on‑site lead for the project, told the board that framing and removal of old windows are essentially complete and that crews are preparing foundation drains and handicap entrance footings.
“We're gonna be finishing up all of the framing,” Peter reported, adding that “all the old windows have been removed and they're gonna be disposed of because they had the asbestos in the in the putty.” He said mechanical, electrical and plumbing subcontractors are scheduled to start rough‑ins in the next week, and that site excavations are in progress to prepare for concrete walls and new underground waste piping for the kitchen and bathrooms.
Peter outlined a contractor schedule that calls for Naylor & Breen to reduce on‑site presence in mid‑February because of general‑conditions cost pressure and then return in mid‑March to complete interior trim, painting and exterior finishing. Board members asked for a clearer cost picture once the next invoices and change‑order totals are posted, and Peter said a fuller picture should be available by the end of January.
The board heard that some unexpected covered‑condition work generated change orders; the chair told members the group is exercising caution on discretionary purchases until the full set of invoices and grant reimbursements are reconciled. The project remains on a path to prepare the building for programming once those finishing phases are complete and funding clarifications are made.
The article is based on the board exchange where Peter summarized construction sequencing, materials handling, and upcoming contractor milestones.