Board approves change order, storm drainage contract and pay application for Big Sioux Levee repairs
Summary
The board approved Change Order #1 adding Sioux Pointe Trail repairs ($97,735), awarded storm drainage installation to RP Constructors ($39,500), and approved Pay Application #3 to Lieber Construction for $377,467.15 for work through April 15, 2025.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Dakota Dunes CID Board approved several actions related to the Big Sioux Levee Repair Project on April 21. The board approved Change Order #1 to include repair of the Sioux Pointe Trail at a cost of $97,735; the motion passed 5-0. The board also approved awarding the storm drainage installation portion of the project to RP Constructors for $39,500 and approved Pay Application #3 to Lieber Construction for $377,467.15 for work completed through April 15, 2025.
These actions were recorded as routine construction contract management items in the minutes; board members voted unanimously on each motion. The approval of the pay application authorizes payment for work performed to date; the change order expands the project scope to add trail repair work in conjunction with the levee improvements.