Engineer estimate places Whitingham highway garage project at $4.74 million; board plans August design work and November bond vote

Whitingham Selectboard · June 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A DEW estimate put the highway garage project cost at $4,743,448 (including $560,000 for a culvert and roughly $500,000 contingency). The board directed meetings with Stevens & Associates and DEW for potential cost savings and set milestones toward an anticipated November bond vote.

Gordon Bristol reported a DEW cost estimate of $4,743,448 for the proposed highway garage. The estimate includes $560,000 allocated to replace a culvert and a contingency line item of about $500,000; Bristol said contingency may fall as the design is finalized. The board had previously chosen sprinkler protection after the Division of Fire Safety adjusted requirements.

Stevens & Associates (S&A) and DEW will meet to identify potential design cost savings; S&A is slated to perform design changes in August, prepare construction documents in November, and work on site design and permitting in July. The Selectboard continues to target a bond vote in November; no bond question or formal tax impact was approved at the meeting.