Hesston approves trail subgrade modification for 1,200-foot section at $39,125 after special meeting
Summary
After tabling the item at the regular meeting, the council at a May 18 special meeting approved applying a subgrade modification to 1,200 linear feet of trail north of the pond for $39,125 based on a Prairie Landworks, Inc. proposal; the vote was 4-0 with one abstention.
Get email alerts on the Trail Subgrade topic
No spam. Unsubscribe anytime.
Discussion of a proposed trail subgrade modification began during the May 11 council meeting and was deferred to a May 18 special meeting for further consideration. Council entered a five-minute executive session on May 11 to consult with the city attorney; no binding action was taken at that time and the council moved to table the change order to the May 18 meeting.
At the May 18 special meeting the council approved applying the subgrade modification to the full 1,200 linear feet of the trail section north of the pond at a lump-sum cost of $39,125, based on Prairie Landworks, Inc.'s 5/15/26 proposal. The motion carried 4-0 with Michael Wallace recorded as abstaining; the minutes identify the price and the specific linear footage.