Council hears plan for two wastewater plant expansions; design contracts to go to July 28 meeting

Amarillo City Council · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff and consultants presented phase-2 engineering work for Hollywood and River Road wastewater plant expansions, outlined funding sources including a $20 million design grant, and described three treatment technologies and CMAR coordination; staff said cost ranges remain wide until 30% design.

City staff and consultants presented predesign and conceptual engineering for two wastewater treatment plant projects that together are central to long-term capacity planning. Donnie Hooper summarized drivers — capacity constraints, aging plants and permitting — and said the July 28 agenda will include two Phase 2 professional engineering service agreements with Kimley Horn for predesign and cost-model development.

Kimley Horn's project manager described evaluating three treatment technologies (conventional activated sludge, membrane bioreactor and oxidation ditch) and the benefits of early CMAR coordination to provide market-based pricing and value engineering. Staff identified a $20 million design grant to cover the first phase and noted two additional loan or grant applications (roughly $60 million each) under review; consultants said total program costs could range into the hundreds of millions, with a staff target to keep the program at or below $1 billion if possible but that final numbers depend on 30% design work.