Airport access road contract executed; terminal hold-room expansion staged pending grant award

Abilene Regional Airport Development Board · March 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Airport staff said the Bonanza Drive access road contract was executed with a change order to keep it within budget; terminal expansion (a 4,700 sq ft hold-room) is in design and staff anticipates a July construction start pending an expected FAA grant announcement in June.

Don said the Bonanza Drive (airport access road) contract was fully executed and a change order reduced the negotiated fee to keep the project within budget; the airport expects to issue a notice to proceed to Bonnke Construction and schedule a pre-construction meeting. A ribbon-cutting or groundbreaking is anticipated once schedules align.

On the terminal expansion, Don said Park Hill (design firm) and Lindbeck (construction manager at risk) continue design work on 'package 1', a proposed 4,700-square-foot expansion of the boarding hold room. He said staff expects an FAA grant decision in June and plans to begin construction in July if funding is awarded; staff will wait to avoid starting work that would not be reimbursed by the grant.