Select Board reviews $200,000 culvert grant; road commissioner explores lower-cost alternatives
Summary
The town received a $200,000 grant toward a culvert replacement estimated at $530,000–$600,000. Road commissioner said a hydraulic study was done and proposed exploring more economical structural alternatives for state approval.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Road commissioner reported that contractors will do shimming the week of the 16th and that a street sweeper is scheduled next week. He reported the town received a $200,000 grant to replace a large culvert, but that the commissioner's estimate of total cost ranged from $530,000 to nearly $600,000. The road official said he had a hydraulic study and would explore alternatives—such as a pipe arch or other structure—if the state will accept them under environmental standards.
The board discussed the grant timeline and the need to develop a more economical design for state approval. The road commissioner said he would spend time developing an alternative project proposal and acknowledged that doing so risks the state rejecting a non-standard approach; the board asked staff to continue consulting with state engineers and to return with a recommended design and budget.