Public works report: two watermain breaks, lift-station delay tied to WE Energies, WWTP awaiting DNR review

Random Lake Village Board · July 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

DPW Director Peter Lederer reported two watermain breaks on Lake Drive, lift-station repairs and a delay in the E Shore Lift Station performance test because WE Energies cannot schedule until July 18; the performance test is now scheduled for July 27 and the WWTP project is awaiting DNR review.

DPW Director Peter Lederer updated the board on multiple public-works items: water meter repairs, new home water service hookups, lift-station repairs, WWTP issues related to a waterline flooding event, removal of stumps on village properties, and two watermain breaks on Lake Drive. Trustee Jamie Vorpahl asked for verification that barricades would be in place for road closures; Director Lederer said the barricades will be in place on Friday.

Director Lederer said the E Shore Lift Station performance test is delayed because WE Energies cannot get out until July 18, so the performance test is scheduled for July 27. President Urbanski said the WWTP timeline is pending the Department of Natural Resources review. These timelines were presented as operational updates; no formal board action was taken at this meeting on the projects.