Engineer: 2026 road plans 75% complete; construction bid targeted for mid‑July

Public Works Committee · May 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Kevin Risch of Clark Dietz told the Public Works Committee that plans for the village's 2026 road projects are about 75% complete, railroad and DNR watermain permits have been submitted (approval expected in ~46 weeks), and the team aims to advertise for construction bids by mid‑July to complete work in 2026.

Kevin Risch, an engineer with Clark Dietz, told the Public Works Committee on May 20 that the goal is "to be out for construction bid by mid-July" so construction can still occur in 2026. He said the plans are roughly 75% complete and that railroad and Wisconsin DNR permits for the watermain have been submitted; Risch estimated it will be about 46 weeks before those permits are approved.

Risch also said the railroad informed project staff it cannot perform crossing pavement work in 2026 because of budget constraints. The committee discussed construction sequencing and timing: Risch estimated a watermain replacement would take about "6–8 weeks," and Chairman Jamie Vorpahl warned the asphalt plant typically shuts down in mid‑November, which constrains paving schedules. The committee did not take a vote on any contract at the meeting and directed staff to continue permitting and bid preparations.