Mountrail County shifts CR3 Palermo North project from gravel to pavement; approves $26.9M construction estimate and $3.5M engineering amendment

Mountrail County Commissioners · January 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved changing the CR3/Palermo North Reconstruction design from gravel to pavement with estimated construction costs of $26,885,000 and approved Sauber Engineering Amendment No.1 adding $3,500,000 for engineering (adjusted not‑to‑exceed $4,460,000).

Mountrail County Commissioners voted on Jan. 7 to change the CR3/Palermo North Reconstruction Project design from gravel to pavement for Phase I and Phase II, with an estimated construction cost of $26,885,000. The board also approved Amendment No. 1 to Sauber Engineering’s contract, increasing the engineering amount by $3,500,000 for a revised not‑to‑exceed total of $4,460,000. Both motions passed unanimously on roll call.

County engineers presented cost and design rationale before the vote; the minutes record that Commissioner Joan Hollekim moved the paving design change and Commissioner John DeGroot seconded the engineering amendment. The board’s action advances a large multi‑phase reconstruction project and commits both construction and additional engineering dollars to the CR3 corridor.