Board approves Pay Application No. 3 as pump shipment delays continue
Summary
DPW Director Peter Lederer told trustees a new pump is being shipped but gas and electric installations remain pending; the board approved Pay Application No. 3 for advance construction 5-0.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
DPW Director Peter Lederer told the board the new pump required for lift-station work has shipped, but gas and electric installations are still pending and the village continues to run on the old lift station in the meantime.
Lederer said future tree cutting will continue after work is completed and that the installation schedule depends on utility hookups. Trustee Chuck Mueller moved to approve Pay Application No. 3 for advance construction; Trustee Rachell Fuller seconded and the motion carried 5-0.
The board approved the payment installment to keep the project moving while staff coordinates final utility work and tree-removal scheduling.