Miramar seeks $21.4M for Historic Miramar drainage project to reduce flooding

City Commission of the City of Miramar · September 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works requested $21.4 million for phase 5 of the Historic Miramar drainage project to regrade swales, add exfiltration treatment and reduce neighborhood flooding; commissioners approved the CIP that includes this allocation.

Public Works presented a large stormwater project targeted at the Historic Miramar neighborhood. Shauna Combs, chief operating officer and public works director, said the FY26 CIP requests $21,400,000 for Historic Miramar drainage project phase 5 to further reduce flooding, improve stormwater flow and strengthen neighborhood resilience.

Combs described the project boundary (bounded by Southwest 68 Terrace and Southwest 25th Street to the north, Sunshine Boulevard to the west, Southwest 64th Avenue to the east and Miramar Parkway to the south) and said the work will include regrading swales and adding exfiltration treatment. The CIP that funds this project was adopted in principle; staff indicated detailed designs and procurement steps will follow and the project will be coordinated with stormwater and utility improvements.