Change order increases Branch Hill Guinea sewer contract by $20,318; adds 140 days
Summary
The Board approved Change Order No. 1 to the Branch Hill Guinea Road Sewer Extension contract with SmithCorp, increasing the price by $20,318.37 to $373,358.37 and granting a non-compensable 140-day time extension (new completion date 08/21/2024).
Get email alerts on the Sewer Infrastructure topic
No spam. Unsubscribe anytime.
The Clermont County Board of Commissioners authorized Change Order Number 1 to the previously ratified contract with SmithCorp, Inc. for the Branch Hill Guinea Road Sewer Extension Project (Project No. 6402-60202). The change order increases the contract by $20,318.37 for a total adjusted contract price to date of $373,358.37 and provides a non-compensable extension of 140 calendar days with a revised completion date of August 21, 2024. The Board approved the change order by unanimous vote.
The change order was authorized to cover additions, deletions, and modifications identified during project execution; the Board directed that the County follow contract administration processes for change orders and time adjustments. The Water Resources Department will track completion in accordance with the revised schedule and contract terms.