Board authorizes change order reducing Newtonsville wastewater contract by $79,095 and extending completion dates

Board of County Commissioners of Clermont County, Ohio · March 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved Change Order No. 3 for the Newtonsville Wastewater Treatment Plant (Part A) project, decreasing the contract by $79,095.10 to a $6,318,398.90 total and granting non‑compensable time extensions for substantial and final completion.

The Board authorized Change Order Number 3 to the contract with Building Crafts, Inc. for Project Number 6402-60117 (Newtonsville Wastewater Treatment Plant Part A). The change order represents a decrease of $79,095.10 for a revised contract price of $6,318,398.90 and includes non-compensable extensions of time: 84 calendar days for substantial completion and 415 calendar days for final completion (revised substantial completion 11/22/2023 and final completion 11/22/2024 as recorded).

The motion was moved, seconded and adopted by roll call without recorded dissent. The change order language covers additions, deletions and modifications with the revised contract price and time schedule recorded in the official minutes.