Supervisor Kerry Jobe said Grade 4 and 5 sewer leaks will be repaired by May under the Consent Order and Agreement; the Cloverleaf pump station needs maintenance and Solicitor Falatovich summarized the dissolution process for the Crabtree Authority.
Get email alerts on the Sewage Infrastructure topic
No spam. Unsubscribe anytime.
Kerry Jobe updated the board on sewage system work, saying Grade 4 and 5 leaks will be repaired by May in accordance with the Consent Order and Agreement. She flagged maintenance needs at the Cloverleaf pump station, noting problems with the can and ladder that will require attention.
Solicitor Falatovich provided a summary of the procedural steps to dissolve the Crabtree Authority; supervisors did not vote on dissolution at the March 19 meeting. Jobe also said township engineers are modeling a Salem Unity buildout and staff are "waiting for numbers" to finalize a Memorandum of Understanding related to the study.