Florence County reports 282 of 346 CPST III/IIIA road projects complete; many district projects advancing

Florence County Council · May 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff told Council 282 of 346 Capital Project Sales Tax (CPST III & IIIA) road projects are complete or under construction and provided district-by-district updates on remaining projects, scopes and SCDOT coordination needs.

County staff and the CPST engineer reported detailed status updates on CPST III and CPST III-A projects across nine council districts, noting that approximately 282 of 346 projects are complete and 16 roads are under construction. The update listed completed projects, work awaiting final invoices, projects in design, and items requiring scope clarification or coordination with the South Carolina Department of Transportation.

Council members asked for clarifications on specific drainage and sidewalk projects and were provided a timeline for design, contracting and pending pay applications. Several district-specific items—such as Holloway Lane design, Oakland Avenue sidewalk design, and Deer Road water-line extension—were highlighted as either near completion or needing further scope work.