Bayside Terrace enters one‑year closeout; inspections to address remaining punch items
Summary
Staff said Bayside Terrace reached final completion in August and that inspectors will address outstanding punch‑list items during the one‑year closeout; staff noted a standing drainage low spot that does not clear within 72 hours and will be evaluated for repair.
Get email alerts on the Project Closeout topic
No spam. Unsubscribe anytime.
Jamieson told the committee Bayside Terrace received final completion in August and the project is now in the one‑year closeout period. Inspectors have reviewed several items and staff plans to coordinate with the contractor to remedy defects that are determined to be workmanship‑related.
He identified one location that holds water (described as a birdbath) that does not drain within 72 hours and said staff will assess whether the solution requires elevation changes or concrete grinding. The secondary egress area associated with the project remains fenced off per the original neighborhood agreement but is still city right‑of‑way and mowed as a drainage easement; there are no current plans to alter its status.
Staff did not request formal action at the meeting and will continue inspections and coordination with the contractor as needed.