Hinkle Bridge work slowed by weather; change order signed to extend construction to March 3
Summary
Great River Engineering reported delays on Hinkle Bridge (BRO-R108(46)) due to holidays and cold weather; the Commission signed a change order to be approved by MoDOT extending construction with a March 3 completion date.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Jake McBee of Great River Engineering told the Commission that work on the Hinkle Bridge project (BRO-R108(46)) has slowed because of recent holidays and cold weather. Presiding Commissioner Joe Wilson signed a change order that will be submitted to the Missouri Department of Transportation (MoDOT) to extend the construction timeline; the minutes record a new completion date of March 3.
The entry notes the reasons for delay and the administrative step of signing the change order, but it does not list contract amounts, new completion guarantees, or revised interim milestones. Additional MoDOT approval is required for the change order to take effect.