Runway 10-28 rehabilitation survey set for April as pavement maintenance closeout continues
Summary
C&S reported that topographical and geotechnical subconsultants are under contract for runway 10-28 rehabilitation, with a survey expected in April; pavement maintenance closeout work is ongoing.
Get email alerts on the Runway Rehabilitation topic
No spam. Unsubscribe anytime.
C&S told the council that topographical and geotechnical subconsultants are under contract for the Runway 10-28 rehabilitation and that the survey work is expected to be completed in April.
Separately, the airport pavement maintenance system project remains in closeout with C&S continuing administrative and oversight tasks. Fence improvement design was also discussed and is expected to start in April pending weather.
The minutes record scheduling and contract status but do not include contract values for the runway work or a firm construction timeline. Staff will report back as survey results and design milestones are completed.