Select Board conditionally approves Pike Industries paving quote, requires 2-inch minimum and revised estimate in seven days
Summary
Board reviewed multiple paving quotes for Boston Post Road, accepted Pike Industries' $66,332 quote subject to an amendment requiring a minimum 2-inch pavement thickness and an updated estimate returned within seven days before final contract signing.
Get email alerts on the Road Maintenance topic
No spam. Unsubscribe anytime.
Board members reviewed four paving quotes for work on Boston Post Road and neighboring intersections; Pike Industries proposed a quote of $66,332 and was discussed as the preferred vendor because of availability and past performance. "For Pike, $66,332 even," one board member stated during discussion; after questions about grind, thickness and base treatment the board amended the motion so acceptance would be conditional on the contractor guaranteeing a minimum 2-inch asphalt thickness and providing an updated estimate within seven days.
The board then voted on the amended motion; members agreed to proceed with Pike on that condition, and staff were asked to obtain the written revision specifying thickness and timing before signing a contract.