Booking‑room project behind schedule; county withholds pay request pending HVAC fixes

Potter County Commissioners Court · August 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County project manager reported the jail booking‑room contract missed its Aug. 5 revised completion date due to HVAC/TAB deficiencies; the county is holding pay request #10 ($187,008.54) and $83,660 in retainage until corrective work and retesting are complete and set a final correction deadline of Aug. 20 before considering liquidated damages.

Project staff told the commissioners the booking‑room portion of the jail project has not met the revised completion schedule because of HVAC problems and failed TAB (testing, adjusting, balancing) reports. The project manager said the first preliminary inspection identified dozens of deficiencies that remain outstanding, and the TAB company failed its inspection; as a result, the county is withholding pay request number 10 for $187,008.54 and $83,660 in retainage until the HVAC items are corrected and retested.

Staff said they would give the contractor a grace period through Aug. 20 to finish the HVAC corrections and complete the required tests; if the work is not complete by that date the manager said the county would ask the court to enforce liquidated damages. The manager emphasized some issues were caused by existing 30‑year‑old equipment that the county itself must repair in order to meet the TAB requirements. Commissioners asked for ongoing updates and for the project team to return to the court if the deadline is missed.