Summary

Project No. 2025-119 (New Water Well #8) for Consolidated Waterworks/Sewerage District No. 2 has been completed and is online near the Bossier Parish Rifle Range; the Jury accepted the Certificate of Substantial Completion and authorized execution of documents.

Assistant Parish Engineer Luke Haney presented photographs and reported that Project No. 2025-119, New Water Well #8 for the West Central Water System, has been completed and is online. Haney recommended acceptance of the Certificate of Substantial Completion, which jurors approved and authorized the Parish to execute necessary documents.

Haney noted the project location near the Bossier Parish Rifle Range; no public comment was recorded on the item and the motion to accept the certificate carried unanimously.