W Road project over budget; Public Works estimates $30,000–$40,000 shortfall

Board of County Commissioners, Jackson County · March 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported the W Road project exceeded its $38,000 budget after restarting work and estimated the county will need an additional $30,000–$40,000 to finish the job; staffing shortages and sequencing near a grain bin also delayed completion.

Public Works Director Scott Kieffaber told commissioners the W Road project had gone over its original $38,000 budget after crews resumed work following a pause. Kieffaber estimated the county would need 'another $30-40,000.00 to complete the project' and said most of the rock needed for the project was already on-site in piles.

Kieffaber described operational constraints: crews paused to allow a farmer to finish hauling near a grain bin, employees have been ill and the department has been short-staffed. He said he had scheduled a 1 p.m. meeting with 'Matt' to discuss adding Matt’s crew and a second water truck to the work. Commissioners discussed shifting crews and directed staff to pursue options to complete the project, including reassessing vendor choices for equipment repairs and fuel availability.