Board approves $247,749.25 in change orders for Whitesville Road soccer expansion

Troup County Board of Commissioners · October 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff said unsuitable soils discovered during construction raised final costs; six change‑order categories added $247,749.25 to the Whitesville Road Soccer Complex project, with work complete and staff proposing capital account funding.

Jay, a county project staffer, briefed commissioners on change orders for the Whitesville Road Soccer Complex expansion. He said the project encountered unsuitable soils during grading and stormwater work, a common occurrence for sites built on former school properties, and that punch‑list and landscaping work remain.

"The list of the 6 different categories, adds up to $247,749.25," Jay said, noting that all work has been verified. Staff said the added cost will be covered from the county’s capital account with the plan to reimburse from SPLOST proceeds as applicable.

Commissioners asked whether funding would come from capital reserves; staff confirmed the plan and said the reimbursement approach mirrors the original contract financing arrangements. The board moved and approved the change orders as presented.