Owner refuses Nedrose #2 easement; attorney outlines eminent domain process
Summary
Terrance Morin will not sign an easement for Nedrose #2; Board attorney Bryan Van Grinsven outlined the Board's eminent domain procedure as a possible next step if legal action is required to secure necessary easements.
Get email alerts on the Nedrose Easements Eminent Domain topic
No spam. Unsubscribe anytime.
Board staff reported that Terrance Morin will not sign a required easement for the Nedrose #2 project. Sarah (Saran) Walker said she received a call from Morin refusing to sign, and the Board discussed options for obtaining the easement.
Water Resource Board Attorney Bryan Van Grinsven outlined the procedure the Board would follow if it chose to pursue eminent domain to acquire the easement. No vote to pursue eminent domain was taken at the meeting; the discussion served to clarify the legal steps that would be necessary should the Board decide to proceed.