Board delays Burlington Dam 3 decision after survey data missing

Ward County Water Resource Board · March 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

HDR presented eight alternatives for Burlington Dam 3, with cost estimates ranging from about $359,100 to $1.33 million; the Board postponed the decision to April because Wildwood Golf Course has not provided promised survey data.

HDR engineer Karli Frohling presented eight alternatives for Burlington Dam 3 — six rehabilitation approaches intended to eliminate the roller effect and two dam-removal options — and shared estimated total costs ranging roughly from $359,100 to $1.33 million, with the Ward County Water Resource District’s share shown as 25% of the least-cost option.

Board members emphasized avoiding impacts to Wildwood Golf Course. Because the golf course had not provided survey data Frohling expected, Jason Zimmerman moved and Roger Kluck seconded to postpone further discussion of the alternatives to the April meeting. The motion passed 5-0. Zimmerman noted a pre-application meeting with the U.S. Army Corps of Engineers indicated SHPO will likely require mitigation tied to the community; Frohling said she had met with Metcalf Archaeology to consider such options.

The memo Frohling presented included specific option cost lines and the Board briefly discussed the difference between dam rehabilitation (which would require temporary and permanent easements) and dam removal (which would require temporary construction easements). No final choice was made; the Board instructed staff to obtain the missing survey data and bring the item back at the April meeting.