Applicant tells Surry planners construction traffic for BESS would be much lower than solar projects
Summary
Applicant representatives told the commission that construction traffic for the Bear Island BESS would involve roughly 75–90 modular containers with about 2–3 heavy deliveries per day during a short delivery window, and that deliveries could be restricted and managed through a traffic management plan with flaggers at narrow points.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Commissioners asked whether the battery project would create the same road impacts previously seen with some solar projects. The applicant representative said construction traffic will be substantially lower than a utility-scale solar installation because battery modules are delivered in fewer, larger containers and are installed modularly.
The applicant estimated 75–90 containers would be delivered during build-out and suggested restricting heavy deliveries to a daytime window to avoid peak local traffic (an example window offered was 9 a.m.–2 p.m.). The applicant also told commissioners they can provide flaggers at narrow road segments and that the formal traffic-management plan will be reviewed during site-plan approval. "We can restrict delivery hours to between 9 and 2, for example, for heavy vehicles," the applicant said when asked about minimizing community impact.