County updates: Historic Courthouse progress, detox facility phase 1 nearing completion

Taos County Board of County Commissioners · April 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff reported steady progress on the Historic County Courthouse renovation (structural reinforcement, temporary roof, exploratory work on the northeast corner) and gave a detailed update on the detox facility (phase 1 sprinkler and mechanical work expected to finish by late May, with recommendation to complete the kitchen before occupancy).

County facilities and construction staff told commissioners that work on the Historic County Courthouse and several community projects is progressing, and that the detox facility's phase 1 work should allow occupancy after fire-suppression and inspections are complete.

"Historic Courthouse is moving along really well," said Richard Sanchez, who outlined demolition, structural reinforcement, temporary roofing and exploratory plaster work in the northeast corner. He said crews had removed the East Alleyway, stripped the old roof and reduced water intrusion, and that some exploratory work was required to confirm whether there is water damage in a corner of the building.

On the detox facility, staff reported that exterior glass has been replaced, floors repaired and sprinkler piping for sleeping areas is being installed. Facilities staff said the sprinkler system inspection should be completed this month and that phase 1 (including fire-suppression and flooring) could be ready by the end of May, but recommended finishing the kitchen before occupant move-in to avoid doubling the later cost. Staff noted supply-price volatility nationally and that the county expects eight to ten active construction projects through the summer, representing roughly $20 million in work.

Commissioners asked about timing, funding and remaining permits; staff said an updated appraisal, approvals from the property-tax division and a finalized lease package remain part of the process before full operational use of some facilities.