Milbank staff report Unity parking, water project progress and public safety exercises
Summary
Staff reported completion of the Unity parking lot and sidewalks, a Twins grant-funded T-ball field, lifeguard training, repair of rubble-site fencing and signage, and that the water supply improvement project is about 25% complete.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Parks and recreation staff reported that parking lot and sidewalks at Unity and along Fourth Avenue have been completed, and that a Twins grant funded construction of a T-ball field; softball dugouts are planned for spring. Parks staff noted Jess Hanson completed lifeguard certification and will teach a class at the high school.
Public works and utilities staff reported repairs on three lift stations, completion of the quarterly toxicity test, rebuilding a jetter pump, and that the water supply improvement project is approximately 25% complete. City staff also reported fence and gate repairs at the rubble site and discussed the possibility of crushing the concrete pile.