Construction at Pages Lane will require up to two months for irrigation work, presenters say

Davis County Commission · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County and agency presenters warned that irrigation work tied to double‑tracking near Pages Lane will require significant closures of irrigation canals and could take about two months, with an aim to finish sooner and to coordinate with county public works.

Presenters told commissioners that certain construction activities will require utility and irrigation work that could temporarily close passages at Pages Lane and nearby crossings. A presenter described the work and estimated duration: "So about about 2 months to do some irrigation underneath the roadway there," and added that the team hopes to complete the work sooner with close coordination with county public works.

Staff said the irrigation canals at that location require attention before track work and that closures will be planned so as to minimize traffic impacts. County staff and the project team discussed notification and sequencing so residents and affected users can prepare for detours and short‑term disruptions.