Board approves ES retaining wall, annex repairs; roof replacement tabled
Summary
The board approved a $31,300 retaining wall/water‑diversion project and a $10,180 repair of annex steps, but tabled a Turner Roofing quote to replace the Quad building roof pending more information.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
John Henry moved to approve a $31,300.00 quote from Pawnee Ready‑Mix (Ricky Edwards) to construct a retaining wall and perform water‑diversion dirt work at the elementary school; Tiffany Higgins seconded and the motion passed on roll call. Later in the meeting the board approved a separate $10,180.00 quote to repair steps and resolve a water issue near the southwest corner of the annex/art room, with John Henry moving and Gary Vance seconding.
A proposal from Turner Roofing to replace the roof, soffits and eaves on the Quad building at the elementary school was discussed but tabled pending further information; Tiffany Higgins moved to table and Gary Vance seconded. The minutes record the roof item as tabled rather than approved, so no contractor engagement is authorized from this meeting's minutes.