Water & Light to fund VFW Arena water‑main replacement; change order will raise GMP for arena project

East Grand Forks City Council · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported that an aging water main (installed in the 1970s) was discovered under the VFW arena parking reconstruction and Water & Light will fund its replacement; the change order will increase the guaranteed maximum price for the arena project but will not raise bonding or sales-tax authorizations.

Design work for the VFW Arena parking reconstruction identified a water main beneath the planned parking area that dates to the 1970s and uses a concrete-asbestos pipe type. Staff said Water & Light reviewed the condition and decided to pay for the replacement to expedite timing and avoid later conflicts with the parking reconstruction.

"The motion or the action in front of you tonight ... is it will look like a change order in our contract ... and because Water and Light is fully funding this portion of the project ... it will increase the guaranteed maximum price at the VFW Arena project by the amount of the water main replacement," Reed Huttman explained. Huttman emphasized there is "no increase to what's authorized for bond, bonding or the sales tax proceeds" because Water & Light is covering the replacement costs.

Council members reacted that doing the replacement now made sense after Water & Light crews discovered the line while beginning work. Staff said a contract amendment form will be included in next week's packet for council approval of the guaranteed maximum price addition.