Public works: CCMG 2027 road measurements complete; staff to file September application
Summary
Public works staff told the board field measurements for the CCMG 2027 roads are complete and have been submitted to the vendor; staff emphasized the application window (September 1–30) and recommended preparing materials early.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The public works director reported the city has completed field measurements for CCMG (Community Crossings Matching Grant) roads targeted for the 2027 application and submitted the documentation to USI, the consultant. "We did complete the field measurements for the CCMG Roads for CCMG 27," the director said, and staff recommended being ahead of the September application window.
Board members discussed vendor estimates for this year's MBH road work and asked staff to bring paving quotes and a capital plan for a replacement truck to the next meeting. Staff said they will provide a truck quote and lead‑time estimate for board approval at the following meeting.