Broadway street project: east side near completion, west side paving expected in September

Red Lodge Public Works Standing Committee · July 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works Director Mike Maple told the committee the Broadway east side subgrade and most concrete work are complete with painting expected around Aug. 10, while the west side is about 50% through excavation with paving anticipated in September.

Public Works Director Mike Maple gave an update on the Broadway street project, reporting the east side’s excavation and subgrade work are finished and most of the required concrete is poured. He said the concrete crew should finish the east side next week and that painting could begin around Aug. 10, with west‑side paving anticipated in September.

Maple said the west side is roughly half complete on excavation and that the concrete crew would begin work there starting Aug. 10. He described the overall street program as progressing well and told the committee the planned sequence is intended to reduce rework and allow coordinated paving and concrete operations.