Library reports footings poured; exterior work to resume when weather warms
Summary
Library contractor poured footings and will return to finish exterior painting and the handicap ramp when overnight temperatures are consistently warmer, the library representative told the Select Board.
Get email alerts on the Library Construction topic
No spam. Unsubscribe anytime.
A representative for the library updated the Select Board on construction progress, reporting that concrete footings have been poured and that some wooden forms remain on site. The presenter said exterior paint and final ramp/sidewalk work will resume once overnight temperatures are reliably warmer.
The library representative noted that the handicap ramp formwork was being completed and that crews will return to finish the remaining exterior work. Board members asked a few scheduling questions and were told the follow-up concrete work would happen in warmer weather. No contract changes or urgent budget requests were raised during the update.