Warrick County reports Westwood drainage pipes replaced; 2nd-quarter report presented
Summary
County staff reported the Westwood Subdivision Sections A and B pipes are 100% replaced with final sodding and watering to finish in 2–3 weeks; staff also presented a Warrick County second-quarter report and thanked Jennifer Curry for the report.
Get email alerts on the Maintenance Update topic
No spam. Unsubscribe anytime.
County staff told the board that the Westwood Subdivision Sections A and B drainage pipe replacements are complete and that remaining finish work (sodding and watering) should be done in the next two to three weeks.
The staff member also presented the Warrick County second-quarter report and thanked Jennifer Curry for preparing the document. The report was described as an outline of office activity; staff said more detailed information is available by request.