Phase IV Sewer Line Work Complete; Change Order Coming to Council

Town of Nutter Fort Council · October 22, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer Ryan Holcomb reported Phase IV sewer line work is complete; contractor will finish about two weeks of concrete and sidewalk work before paving, and the engineer will present a change order at the next meeting covering concrete steps, stored materials and quantity adjustments.

Engineer Ryan Holcomb told the council that Phase IV sewer line work is complete and that the contractor has approximately two weeks of concrete and sidewalk work remaining before paving begins. He said a change order addressing concrete steps, stored materials and quantity adjustments will be presented at the next council meeting.

The engineer also noted that one or two pay applications remain for Phase IV closeout; council members were informed of the planned paving sequence and upcoming administrative action to approve the change order and pay applications at a future meeting.