Select Board approves $25 per-plow increase for west-side contractor amid bridge delay
Summary
With the Fiddlehead Bridge unfinished, the board approved a $25 increase to the per-plow bid for the west side, raising contractor Scott Spencer’s rate to $225 per plow to cover extra miles. The motion was moved by Denis Royer and seconded by Tim Simpson and recorded as passed.
Get email alerts on the Public Works Plowing topic
No spam. Unsubscribe anytime.
Highway Foreman Shane Heath informed the Select Board that, because the Fiddlehead Bridge work remains incomplete, contractor Scott Spencer requested an additional $25 per plow to cover extra mileage on the west side. Chair Denis Royer moved to add $25 per plow to Spencer's west-side bid, raising the rate to $225 per plow; Tim Simpson seconded the motion and the board recorded the motion as passed.
The board’s action responds to increased route mileage caused by the incomplete Fiddlehead Bridge. The transcript does not record a roll-call vote or dissent; it records the motion, second and that the motion passed.