Council approves night‑work noise permit for pavement preservation

Pleasant Grove City Council · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a variance to the City Noise Ordinance allowing Geneva Rock Products to perform pavement preservation (level course, scrub seal, micro surfacing) between 10:00 p.m.–7:00 a.m. as needed from May 1 through August 31, 2025; staff will notify the public when night work is planned.

Public Works Director Neal Winterton explained that pavement preservation work sometimes requires nighttime operations to avoid traffic conflicts and meet construction timelines. The council approved a permit to exceed the City’s Noise Ordinance to allow Geneva Rock Products to perform level course, scrub seal and micro surfacing from 10:00 p.m. to 7:00 a.m. between May 1 and August 31, 2025, and directed staff to provide as much public notice as possible when night work is scheduled.

Winterton said no night work was scheduled at present but staff needs the flexibility to respond to deadlines and traffic management concerns. “Work on leveling has already begun with the next phase being chip seal followed by the micro surfacing,” he said; the council approved the permit unanimously.