Tunbridge explores site study and design for four-bay town garage; architect estimates planning at 11–12% of project

Tunbridge Selectboard · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Selectboard discussed plans for a four-bay town garage and asked architect Andrew LaRosa to begin site and design planning. LaRosa said planning costs would be about 11–12% of the budget and recommended a location assessment as the first step; the town said it hopes to build within five years.

Vice Chair Mike McPhetres told the Selectboard the town is considering a new four-bay town garage and has started preliminary planning work with architect Andrew LaRosa.

LaRosa introduced himself and his background and told the board the first step is to study potential sites and determine which building type — wood or metal — best fits the location. He said features used in garages he has worked on have included radiant floors. LaRosa estimated that planning and design would run “about 11–12% of the budget,” and he offered to produce an outline of options for the board.

McPhetres said the town’s target for building is within the next five years and that the board wanted direction on how to begin the process. Road-report contributor Rodney Hoyt asked about how much of the project budget would be devoted to planning; LaRosa reiterated the 11–12% estimate.

Next steps recorded in the meeting: LaRosa will prepare an outline of design options and a site-assessment recommendation; the board did not set a formal schedule beyond stating a multi-year horizon for construction.