Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects Payments topic
No spam. Unsubscribe anytime.
Board approves pay applications totaling hundreds of thousands for force main and maintenance building
Summary
The Board approved Pay Application #6 to SubSurfco for $96,795.55, SRF drawdown Request #5 for $819.00, and Pay Application #6 to L&L Builders for $348,856.54 for the CID maintenance building; motions passed 5-0.
Get email alerts on the Capital Projects Payments topic
No spam. Unsubscribe anytime.
The Board approved Pay Application #6 to SuBSurfco, LLC for the SRF Force Main project in the amount of $96,795.55 for work completed through Dec. 8, 2025. It also approved the FINAL SRF Force Main Drawdown Request #5 for $819.00 from State Revolving Fund Loan C461035-01. In a separate motion the Board approved Pay Application #6 to L&L Builders for the Dakota Dunes CID Maintenance Building in the amount of $348,856.54 for work completed through Nov. 30, 2025. All motions passed unanimously.
Board members did not record further discussion in the minutes beyond approval of amounts and vendor names; the approvals authorize payment for work completed to date on the listed projects.