Board approves L&L Builders amendment, sets guaranteed maximum price at $2.19 million
Summary
On Sept. 23, 2025, the Dakota Dunes CID board approved Amendment No. 1 to the L&L Builders agreement (Consensus Doc 410), establishing a new guaranteed maximum price (GMP) of $2,187,480.00; the motion passed 4-0.
Get email alerts on the Contract Amendment topic
No spam. Unsubscribe anytime.
The Dakota Dunes Community Improvement District Board of Supervisors voted to approve L&L Builders Agreement Amendment No. 1 to Consensus Doc 410 on Sept. 23, 2025, setting the board-authorized guaranteed maximum price at $2,187,480.00. The motion to approve was made by Ms. Finzen and seconded by Ms. Shanafelt and passed unanimously, 4-0.
The amendment was presented as part of the construction contracting agenda for the CID maintenance building; the minutes record the new GMP but do not provide a line-item budget or explanation of contingency allowances. Todd Benson of L&L Builders was present at the meeting. The board did not record any dissent or conditions attached to the approval.