Summary
The Dakota Dunes Community Improvement District Board of Supervisors unanimously awarded multiple bid packages for a new CID maintenance building on Sept. 23, 2025, including concrete, carpentry, HVAC, plumbing, electrical, paint and earthwork contracts totaling several hundred thousand dollars across packages.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
The Dakota Dunes Community Improvement District Board of Supervisors on Sept. 23, 2025, voted unanimously to award a series of construction contracts for the CID maintenance building. Chairman Beaulieu presided; Mr. Wetz moved and Ms. Finzen seconded the motions, which passed 4-0.
The board awarded Bid Package No. 03-1 (Concrete) to L&L Builders for $239,231.00 and Bid Package No. 03-2 (Concrete floor finishes) to L&L Builders for $9,139.00. Gingerich Structures won Bid Package No. 06-1 (rough carpentry and pre-engineered wood frame) for $239,600.00 and Bid Package No. 07-1 (insulation) for $51,400.00. L&L Builders was also awarded Bid Package No. 06-2 (finish carpentry, hollow metal doors & frames) for $52,500.00 and Bid Package No. 09-2 (resilient base) for $1,100.00. Day's Door Company received the award for Bid Package No. 08-1 (sectional overhead doors) for $60,965.00. Tri-State Drywall was listed as awarded Bid Package No. 09-1 (gypsum board assembly) for $17,028.00; the minutes state that "no bids were received for this bid package" and that the award was recommended by L&L Builders, the construction manager at risk. Reich Painting won Bid Package No. 09-3 (paint work) for $11,637.00. Plumbing, HVAC, electrical and earthwork packages were awarded to Hander Incorporated ($117,900.00), CW Suter Services ($90,500.00), Ward Electric Company, Inc. ($159,000.00), and Lieber Construction ($61,404.61), respectively. Each award was moved by Mr. Wetz, seconded by Ms. Finzen, and recorded as passing 4-0.
The board's minutes note the number of bids received for each package where specified (ranges from one to seven bids). The record shows Todd Benson of L&L Builders was present at the meeting to answer questions. No public comments were received during the public-comment period.