Council awards Dayton Parkway access road bid; lowest bid $1.711 million, wetland mitigation noted

Dayton City Council · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved awarding the Dayton Parkway access road contract after staff reported 12 bids with the low bid of $1,711,000 and discussed wetland mitigation credits (~$456,000) and anticipated 50/50 financing; motion to award passed on a voice vote.

Staff presented the Dayton Parkway access‑road project and recommended awarding the contract after soliciting bids. The city received 12 bids; the lowest responsive bid was $1,711,000. Staff noted bids were competitive and that wetland mitigation credits for the project will cost approximately $456,000.

The project schedule calls for starting construction in early September if property closings and financing occur on schedule; staff described an interim completion target of Nov. 15 to get utilities and a base pavement layer in place for winter and a planned final paving/mill cycle in spring 2027 with final completion likely in 2028. Council moved and approved the award; staff said the project had already been budgeted and that the financing plan anticipated a 50/50 split with future tax‑abatement bond proceeds supporting cash flow.

Council members asked about bid contingencies and cancellation language; staff confirmed the bid documents allowed cancellation in the event financing does not materialize, and said they would return with a recommendation memo to the council as bids were evaluated.