County to vote Tuesday on Springville paving and Sprayberry Road pipe replacement
Summary
Staff asked commissioners to record and sign a previously drafted paving agreement with Springville (county share $12,450; Springville $3,922.50) and to approve a Riverside pipe replacement project (combined figures discussed ~$22,000). Both items will be placed on Tuesday's agenda for formal approval.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
County staff presented two infrastructure items for formal action on Tuesday: a Springville paving agreement and a pipe replacement project on Sprayberry Road in the Riverside area.
Clay Phillips said the Springville agreement — originally discussed months earlier and signed by Springville’s council — specifies a county contribution of $12,450 and a Springville contribution of $3,922.50 for ball‑field parking lot paving. “That is correct, sir,” Phillips said when confirming the figures; staff asked the commission to vote to record and sign the agreement at Tuesday’s meeting.
On Sprayberry Road, staff described a failing corrugated metal pipe beginning to cave in; the plan calls for two 20‑foot sections (40 feet total) and upsizing from a 48‑inch pipe to 60–68‑inch to better handle future development. Phillips gave a combined project figure (two figures combined to approximately $22,000) and recommended proceeding. Commissioners directed staff to place both items on Tuesday’s agenda.