At‑a‑glance: recommended sewer projects and estimated costs from master plan
Summary
The master plan lists one immediate project (E‑1) estimated at $531,000 and four future projects (10‑1, 10‑2, B‑1, B‑2) totaling about $1.42 million in 2024 dollars; project costs include 20% for engineering/admin and contingencies.
Get email alerts on the Budget topic
No spam. Unsubscribe anytime.
The consultant's capital facility tables and appendices list recommended projects and order‑of‑magnitude cost estimates (2024 dollars). The existing deficiency project (E‑1) is estimated at $531,000 and involves a 30" jack and bore under State Street and installation of a 15" gravity line. Ten‑year projects include installing 800 ft and 1,100 ft of 10" gravity line (estimated $336,418 and $462,575). Buildout projects include two 15" gravity line segments (estimated $72,000 and $546,000). The master plan notes cost‑estimate accuracy at the master‑plan level is wide (roughly ‑50% to +100%) and recommends additional survey, flow monitoring and design before construction.
These projects remain recommendations in the plan; the transcript shows presentation and tables but does not record appropriation or formal contract awards during the Jan. 14 meeting.