Council hears $130M wastewater‑treatment plan, $17M pump‑station design and routing details

Bryan City Council · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff presented plans for an East‑side pump station and new wastewater treatment plant with an estimated plant cost of about $130 million, pump‑station construction at roughly $17 million and a force main design near $12 million; council framed the project as essential for future growth.

City engineering staff presented the first phase of a multi‑component sewer improvement project intended to serve Bryan's east side and future growth.

Dr. Jason Barfnick described a pump station designed to intercept flows from the Burton Creek sewer basin and pump them across Highway 158 toward Oakmont and the planned new wastewater treatment plant. Barfnick said the pump station's dry average daily flow is projected at 3,000,000 gallons with peak wet weather capacity of 21,000,000 gallons.

He outlined estimated costs: roughly $1.2 million for design and about $17 million to construct the pump station, about $12 million design for the force main, and a plant cost currently estimated at $130 million plus another roughly $30 million for the gravity line. Council members framed the work as a long‑term infrastructure investment to enable economic development and residential expansion on the city's east side.

Barfnick said council previously approved design work on the larger wastewater treatment plant (a $5.3 million contract), and staff is now approximately 30–40% through the plant design and route planning for the interceptor line.

Next steps: continue detailed design, complete right‑of‑way and route work, and return with bidding and financing recommendations when the design and procurement phases conclude.