Hughes Road drainage work nearing completion; mayor urges patience amid weather delays
Summary
Public works said the Hughes Road drainage project is about 90% complete and on track for asphalt work before school starts if dry weather holds; council and staff discussed detour impacts, timing and staging for final paving and cleanup.
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
The city’s public-works representative, Mr. Magdaleno, told the council the Hughes Road drainage project is roughly 90% complete and that crews remain on schedule ‘‘to be done end of September, cleaned up in October,’’ though he warned rain could delay asphalt deliveries and push final paving into the weeks before school starts. He said temporary detours using Robinson Road were installed to avoid a multi-mile diversion and acknowledged those temporary repairs have deteriorated in recent rain.
Magdaleno described the drainage features already working in wet weather—‘‘I’ve got plenty of video and pictures of this water moving through these RCBs… and going to the outfall and getting in our bayou. So it’s working,’’ he said—and asked residents for patience while crews complete the overlay work. Council members pressed for clearer communication about detour timing; the administration said it would send text alerts and post updates to social media when firm dates for work and lane changes are available.