Commissioners approve CR 10 easement and revised CR 1 rebuild plan with MWEC cost-share
Summary
The Board approved a road easement with North Dakota Trust Lands for CR 10 and a revised Notice of Intent with Mountrail Williams Electric Cooperative for a north and south CR 1 rebuild, including MWEC estimated costs and estimated cost-share numbers.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Road & Bridge Engineer Jana Hennessy asked the Board on June 3 to approve a right-of-way easement from North Dakota Trust Lands needed for the CR 10 project. The Board approved the easement for the SE¼ and SW¼ of Section 16, Township 154, Range 89 on a unanimous roll call.
Hennessy also presented a revised Notice of Intent with Mountrail Williams Electric Cooperative (MWEC) for a north-end rebuild on County Road 1 with an estimated cost of $375,225 not to exceed $412,746 (MWEC 50% estimated cost share reflected in the ceiling) and a south-end rebuild estimated at $350,450 not to exceed $385,504 (no MWEC cost share). State's Attorney Wade Enget provided an update on related right-of-way easements. The Board approved the revised Notice of Intent and associated signatures by motion and roll call.
The project approvals carry required signatures and set project cost ceilings; the engineering office and legal staff were directed to proceed with easement documentation and coordination with MWEC.